• Post Reply Bookmark Topic Watch Topic
  • New Topic
programming forums Java Mobile Certification Databases Caching Books Engineering Micro Controllers OS Languages Paradigms IDEs Build Tools Frameworks Application Servers Open Source This Site Careers Other Pie Elite all forums
this forum made possible by our volunteer staff, including ...
Marshals:
  • Campbell Ritchie
  • Jeanne Boyarsky
  • Ron McLeod
  • Paul Clapham
  • Liutauras Vilda
Sheriffs:
  • paul wheaton
  • Rob Spoor
  • Devaka Cooray
Saloon Keepers:
  • Stephan van Hulst
  • Tim Holloway
  • Carey Brown
  • Frits Walraven
  • Tim Moores
Bartenders:
  • Mikalai Zaikin

Disaster Recovery planning

 
Greenhorn
Posts: 7
  • Mark post as helpful
  • send pies
    Number of slices to send:
    Optional 'thank-you' note:
  • Quote
  • Report post to moderator
I am planning to highlight Availability during catastrophic failures as Risk with Mitigation plans documented.

However For 99.99% stated availability, is it expected that I plan for Disaster Recovery in the Deployment Diagram?
 
author & internet detective
Posts: 41860
908
Eclipse IDE VI Editor Java
  • Mark post as helpful
  • send pies
    Number of slices to send:
    Optional 'thank-you' note:
  • Quote
  • Report post to moderator
You need to show you've planned for disaster, yes. Probably via failover of some sort. It's likely you wouldn't have a recovery plan though - just one direction.
 